  • EPC warehouse production with an overall 3600 square meter area. Baghdad, Iraq -2012.
  • Implementation of Wellhead, well pad flow line services. – Basra, Iraq – WQ -1 2012.
  • Installation of EPC of HVAC & 1300M Length ducts of different sizes for AL-Quduss power planet.Baghdad Iraq-2012
  • Installation of a three floor steel structural building. Al Maqel, Basra, Iraq – 2013.
  • Project consisting of installation of EPC oil storage tanks and loading arms with a total
  • capacity of 14,000 cubic meters. AL-Umarah- Iraq 2014.
  • Insulation and cladding for six HFO Storage tanks, Basra, Iraq- 2015.
  • Installation of 10 heat exchangers connected with water pipes and oil pipes. Basra, Iraq-2015
  • Creation of HFO pipe line for Shatt Al-Basrah power plant, Basra, Iraq- 2016.
  • Pipe Cladding and insulation work for south Baghdad power plant. lraq-2017.
  • Pipe Insulation and Clading work for Zubair Power plant for ENI in Zubair-Basrah Iraq 2017
  • Lighting poles and MEP work Basmaia power plant.Iraq-2017
  • Pipe Cladding and insulation work for gas cooling system in Gas compressing station for
  • Samasung .Hammar basrah Iraq power plant. lraq-2017.
  • Excution water supply, swage and Electricity network for Bayty residential project 2015- 2018 Tikrit (accompany al Buruj).
  • Steel Structure erection work 203 Ton for Karbala refinery. lraq-2019
  • Sandwitch Panel installation work 15,000 M2 for Karbala refinery. lraq-2020
  • Raisd Floor, False ceiling and Gypsum Board installation work for Karbala refinery .Iraq-2020
  • 2022 qualifying to repair system(soil water)chiller workshop Building the role of single people1
  • installing a bridge scale for trucks to a Al Khayrat gas power plant (2023).
  • Repair and rehabilitation of gas ducts and diffuser for turbine gas units Of 4th, 5th and 6th, 7th, 8th, 9th and 10th For Al Khayrat gas power plant.
  • Repair diffuser for 1st unit of Al Qudus gas power plant.2024